PROJECT
QATAR ALUMINIUM SMELTER
PROJECT OWNER | QATALUM - QATAR ALUMINUIM
CLIENTS | FIVES SOLIOS | SNC LAVALIN | FATA
DURATION | 2010 - 2011
PROJECT SCOPE
Mechanical Installation of more than 1000 Tons of process equipment, and piping for the Fume Treatment Plant inside & outside the Potrooms of the Qatar Aluminum Smelter Project (Qatalum).
Scope of works also included support installation services for the client to help them wrap-up the project after a defaulting contractor.
PROJECT HIGHLIGHTS
​​
-
Completed the originally assigned works within the very challenging timeline of 90 days whilst remaining within the project’s budget. The project was highly demanding where we were commissioned to replace a defaulting contractor and were under high pressure by the client and the plant owner to meet milestones.
-
Managed to gain the trust of the client and continuously extend the scope of supply to include many services such as punchlist clearing activities, commissioning assistance and technical support services.
-
Succeeded to remain with the client as the last contractor onsite, offering them various services, out of more than thirty (30) subcontractors.
-
Extended the original contract value to reach more than 400% of its original value.